Project Type Value (B$) Clients Status
Upgrading Of Lamunin Road Earthworks & Widening Of Road 2,339,061.60 Syarikat Jurubima Done
Stadium Car Park Earthworks & Foundation 31,064.22 Maxwell Sdn Bhd Done
Muara A Project Earthworks & Foundation 146,470.51 Maxwell Sdn Bhd Done
Muara B Project Earthworks & Foundation 27,370.62 Maxwell Sdn Bhd Done
Kapok Project Earthworks & Foundation 33,994.31 Maxwell Sdn Bhd Done
Serasa Project Earthworks & Foundation 12,045.31 Maxwell Sdn Bhd Done
Batu Marang Project Earthworks & Foundation 12,056.50 Maxwell Sdn Bhd Done
Tamoi Project Earthworks & Foundation 131,303.69 Iriyal Sdn Bhd Done
Beribi Project Earthworks & Foundation 30,000.00 Pengiran Hamdan Done
Teraban A Project Earthworks & Foundation 63,852.84 Sabani Enterprise Done
Teraban B Project Earthworks & Foundation 58,733.33 Sabani Enterprise Done
Tanah Jambu Project Earthworks & Foundation 129,000.00 Lau Enterprise Company Done
Drainage Improvement Project Drainage Improvement 6,626,236.10 Abdul Khalid Latif General Contractors 80.00%
Interchange At Pusak Ulak Road Drainage Improvement 3,805,225.00 Swee Sdn Bhd 5.00%
Lambak Kanan Low Cost Housing Scheme Earthworks & Foundation 4,384,177.50 Lau Enterprise Company 5.00%

 